• Description:
    The project includes paving the remainder of Caswell Lakes Road and Bendapole Road. Currently, Caswell Lakes Road is paved approximately one mile from its intersection with Hidden Hills Road. Proposed construction will also rebuild and pave Passthebait Avenue and Lostaspinner Street.
  • Benefits:
    Benefits include improved quality of travel, dust control, and reduced maintenance costs.
  • Status:
    The anticipated schedule is to pave Caswell Lakes Rd this summer in 2025. Construction of future phases will proceed as funding allows.
  • Cost:
    Estimated total cost: $1,989,000.
  • Schedule:
    Construction of Phase 1 started in fall of 2024 with final completion in fall of 2025.