Edgerton Parks Rd - Mtn Trails Drive Upgrade & Pathway
Description:
This project will provide a non-motorized pathway along the north side of Edgerton Parks Road and west side of Mountain Trails Drive from Palmer-Fishhook Road to the Government Peak Recreation Area (GPRA) parking lot. Improvements to Edgerton Parks Road are also included in the project.Benefits:
Provide a safe location, out of the vehicle traffic lanes, for people walking, running, and biking to travel between Palmer-Fishhook Road and Government Peak Recreation Area (GPRA), one of the most popular recreation sites in the borough.Status:
Phase 1 is under construction with substantial completion anticipated fall 2025. Phase 2 will include pedestrian facilities across the Little Susitna River.Cost:
Estimated total cost: $8,500,000.Schedule:
Future phases are dependent on funding.Links: