• Description:
    The purpose is to extend the pedestrian/bike pathway along the west side of the Old Glenn Highway from Plumley Road south to the Knik River Public Use Area. The existing pathway connects Palmer to the Butte community and ends at Sodak Circle. This project will extend the pathway from Sodak Circle to Knik River.
  • Benefits:
    The project will increase safety and access for vehicles, pedestrians, and bicycles by providing a pathway connection to the Knik River Public Use Area. It will also improve drainage and snow storage.
  • Status:
    Design is 75% complete with right-of-way needs and utility conflicts identified. Acquisition of right-of-way and utility relocation efforts are underway.
  • Cost:
    Estimated total cost: $1,800,000.
  • Schedule:
    Construction depends on availability of funding.