• Description:
    Improve Lucille Street and pathway from Spruce Street to Schrock Road, including resurfacing, drainage, and adding a turn lane at Tanaina Elementary.
  • Benefits:
    Reduce traffic congestion, enhance pedestrian and vehicle safety, increase reliability of transportation system, and provide transportation choices for residents. Phase 1 resurfaced Lucille Street from Seldon north to Schrock. Phase 2 will improve drainage, add a turn lane at Tanaina Elementary, and improve the pathway from Seldon Road south to Spruce Street.
  • Status:
    Phase 2 is at the 65% design stage. The team is beginning right-of-way acquisition and utility coordination.
  • Cost:
    Estimated total cost of phase 2: $8,900,000.
  • Schedule:
    Construction of phase 2 is anticipated in 2026.