1a | Glenn Highway MP 34-42 Reconstruction Widen to 4 Lanes Parks Hwy to Palmer | Congestion Relief | $56.00 | FHWA | 2,3 |
2 | Glenn Highway - Erosion Protection MP 63 and MP 64 | Safety, Asset Management | $5.60 | FHWA | 1 |
3 | Knik Goose Bay Road - Centaur Avenue to Vine Road Widen to 4 Lanes | Congestion Relief | $83.20 | FHWA | 4,5 |
4 | Knik Goose Bay Road - Vine Road to Settlers Bay Drive Widen to 4 Lanes | Congestion Relief | $27.20 | State Bond/FHWA | 5 |
5 | Parks Highway/Talkeetna Spur Road Pedestrian Improvements | Safety | $3.17 | FHWA | 7 |
6 | Parks Highway MP 43.5-48.3 - Lucus Road to Pittman Road Widen to 4 Lanes | Congestion Relief | $15.10 | FHWA | 4,7 |
7a | Parks Highway MP 48.8 to 52.3 - Pittman Road to Big Lake Road Reconstruction Widen to 4 lanes | Congestion Relief | $42.80 | FHWA | 7 |
8 | Point MacKenzie Road Improvement, MP 21.8 to 23 | Congestion Relief | $1.23 | FHWA | 5 |
9 | Seward Meridian Parkway - Palmer-Wasilla Highway to Seldon Road Widen to 5 Lanes | Congestion Relief | $29.30 | FHWA | 3,4,6 |
10a | Vine Road Improvements - Knik Goose Bay Road to Hollywood Boulevard - | Congestion Relief | $2.00 | FHWA | 5 |
11a | Wasilla Fishhook Road/Main Street (Yenlo Couplet) | Congestion Relief | $5.70 | FHWA | 4 |
12 | Palmer-Wasilla Highway - Widen to 3 Lanes | Safety | $21.80 | HSIP | 1,2,3,4 |
13a | DOT&PF MSB Intersection Improvement Program | Safety | $5.00 | HSIP | Various |
14a | Glenn Highway MP 53-56 Reconstruction - Moose Creek Canyon | Asset Management | $3.00 | FHWA | 1 |
15a | Glenn Highway MP 84.5-92 Rehabilitation - Long Lake Section | Asset Management | $5.00 | FHWA | 1 |
16a | Glenn Highway Rehabilitation MP 79-84.5 | Asset Management | $7.70 | FHWA | 1 |
17a | Parks Highway Bridge Replacement - Montana and Sheep Creek | Asset Management, Safety | $0.73 | FHWA | 7 |
18 | Parks Highway MP 90-99 Rehabilitation (Trapper Creek) | Asset Management | $21.00 | FHWA | 7 |
19 | Parks Highway MP 99-123.5 Rehabilitation | Asset Management | $35.76 | FHWA | 7 |
20a | Parks Highway MP 163-183 Rehabilitation | Asset Management | $0.59 | FHWA | 7 |
21 | Parks Highway MP 183-192 Rehabilitation | Asset Management | $0.92 | FHWA | 7 |
Medium-Term (2020-2025) | |||||
1b | Glenn Highway MP 34-42 Reconstruction Widen to 4 Lanes Parks Hwy to Palmer | Congestion Relief | $27.30 | FHWA | 2,3 |
7b | Parks Highway MP 48.8 to 52.3 - Pittman Road to Big Lake Road Reconstruction | Congestion Relief | $15.50 | FHWA | 7 |
9b | Seward Meridian Parkway - Palmer-Wasilla Highway to Seldon Road Widen to 4 Lanes | Congestion Relief | $13.40 | FHWA | 3,4,6 |
10b | Vine Road Improvements - Knik Goose Bay Road to Hollywood Boulevard | Congestion Relief | $8.50 | FHWA | 5 |
11b | Wasilla Fishhook Road/Main Street (Yenlo Couplet) | Congestion Relief | $27.10 | FHWA | 4 |
13b | DOT&PF MSB Intersection Improvement Program | Safety | $15.00 | HSIP | Various |
14b | Glenn Highway MP 53-56 Reconstruction - Moose Creek Canyon | Asset Management | $58.00 | FHWA | 1 |
17b | Parks Highway Bridge Replacement - Montana and Sheep Creeks | Asset Management, Safety | $25.06 | FHWA | 7 |
20b | Parks Highway MP 163-183 Rehabilitation - | Asset Management | $44.00 | FHWA | 7 |
22a | Knik Goose Bay Road - Settlers Bay to South Alix Drive Widen to 4 Lanes: Design, ROW, Utilities | Congestion Relief | $8.20 | FHWA | 5 |
23a | Parks Highway Alternative Corridor - Seward Meridian Parkway to Knik Goose Bay Road: Design, ROW, Utilities | Congestion Relief | $12.60 | FHWA/State | 4 |
24 | Glenn Parks Interchange - Hospital Access Improvements 2nd Access to Hospital | Safety/Access | $12.00 | HSIP | 2,3 |
25 | Old Glenn Highway - New Glenn Highway to Airport Road | Congestion Relief | $12.00 | State | 2 |
Ongoing DOT&PF Asset Management and Safety Improvement Program: Annual funding for future asset management and HSIP at $4.0 million/year. | Asset Management and Safety | $24.00 | FHWA/HSIP | All | |
Long-Term (2026-2035) | |||||
10c | Vine Road Improvements – Hollywood Boulevard to the Parks Highway | Congestion Relief, Connectivity, Safety | $33.50 | FHWA | 4,5,7 |
16b | Glenn Highway Rehabilitation MP 79-84.5 | Asset Management | $36.30 | FHWA | 1 |
22b | Knik Goose Bay Road - Settlers Bay to South Alix Drive | Congestion Relief | $37.80 | FHWA | 5 |
23b | Parks Highway Alternative Corridor Segment I: Parks Highway/Seward Meridian to Knik Goose Bay Road | Congestion Relief | $132.40 | FHWA/State | 4 |
26 | Palmer Wasilla Highway: Seward Meridian Parkway to Fred Meyers 5 lane | Congestion Relief | $30.00 | FHWA | 4 |
27 | South Big Lake Road - North Shore Drive to Hollywood Road Rehabilitation | Asset Management | $5.00 | State | 5 |
28 | Big Lake Road - North Shore Drive to Parks Highway Reconstruction Widen to 4 Lanes | Congestion Relief | $5.00 | FHWA | 5,7 |
29 | Bogard Road Between Seldon and Trunk Widen to 4 Lanes | Congestion Relief Capacity | $49.00 | State | 1,3 |
30 | Palmer-Wasilla Highway Extension Reconstruction Widen to 4 Lanes | Congestion Relief Capacity | $20.00 | FHWA | 4 |
31 | Parks Highway Alternative Corridor Segment 2: Knik Goose Bay Road to Vine Road: Design, ROW, Utilities , Construction | Congestion Relief | $160.00 | FHWA/State | 4,5 |